Power Pole (File)

Florida Power & Light Transmission Line Project Approved

State Department of Environmental Protection Secretary Shawn Hamilton issued a final order Thursday approving a Florida Power & Light plan to build an 80.5-mile transmission line from Okeechobee to DeSoto counties.

State Department of Environmental Protection Secretary Shawn Hamilton issued a final order Thursday approving a Florida Power & Light plan to build an 80.5-mile transmission line from Okeechobee to DeSoto counties.

The 230-kilovolt transmission line, which also received a sign-off in June from the state Public Service Commission, will connect substations in Okeechobee and DeSoto counties, while crossing parts of Highlands County. In an application filed in April, FPL said the transmission line is planned to be in service by December 2025.

The utility pointed to a need to upgrade its system to meet increased power demands in a region that includes Collier, Lee, Hendry, Charlotte, Glades, Sarasota, DeSoto and Manatee counties.

In the news: Florida Gov. DeSantis Targets China, Other Hostile Countries

“FPL evaluated multiple transmission alternatives for meeting this identified need, which resulted in the selection of the project,” the application said. “The project presents the best alternative, taking into account the demand for electricity, enhancing electric system reliability and integrity and addressing the need for abundant, low-cost electrical energy to assure the economic well-being of the citizens of this state.”

The proposal was initially sent to an administrative law judge, with a hearing scheduled for this month. But the Department of Environmental Protection and FPL proposed canceling the hearing.

An administrative law judge agreed, sending the issue back to the department for a final order under a law known as the Florida Electric Transmission Line Siting Act.

“Having reviewed the matters of record and being otherwise duly advised, the secretary concludes that, if constructed and operated in accordance with the evidence presented in the record and … conditions of certification, the project will serve and protect the broad interest of the public and should be approved,”

Visit Tampafp.com for PoliticsSports, and National Headlines. Support journalism by clicking here to our GiveSendGo or sign up for our free newsletter by clicking here

Android Users, Click Here To Download The Free Press App And Never Miss A Story. Follow Us On Facebook Here Or Twitter Here.

Copyright 2022 The Free Press, LLC, tampafp.com. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.

Login To Facebook To Comment
Share This: